Village of Williamsville — Historic Preservation Commission
Williamsville's preservation commission heard a citizen nomination to landmark the Ellicott Creek dam the village has $2 million to replace. Village DPW records traced it to a 1929 village bond, not the WPA, and members doubted enough of it is original. Decision set for December 15. Also: the mill-wall hearing closed without opposition.
The village wants to take its Ellicott Creek dam out. A resident wants it declared a landmark first. On Tuesday the Historic Preservation Commission held the public hearing, and the hour that followed was less a debate about sentiment than an audit of what, physically, is still there to protect.
The nomination came from James Walfran[*], who presented it himself. He asked the commission to designate the gated structure at Island Park under Chapter 47 of the Village Code, describing it as a Depression-era Works Progress Administration project and a rare surviving example of its type — a low-head dam with concrete piers and manual lift gates. He said a search of the state's dam inventory turned up nothing comparable in Western New York, and that the piers could be kept and engineered around, as an interpretive site or a pedestrian crossing, without making the dam work again. Landmarking it, he said, is “critical” to halting demolition.
He was explicit that he is not asking the village to restore it to service: “I didn't ask for it to be a fully functional dam. I asked it to be declared as a historic site.”
A second speaker, who did not give a name on the recording, opposed the designation. The dam, she said, has not worked as intended for about six years, maintaining it costs taxpayers, and the village has $2 million secured to remove it and build a passive weir that would improve water circulation around Island Park. “Age alone does not make a structure historically significant,” she said, proposing photographs, records and signage instead.
Then the village's Department of Public Works laid out what its archives hold — and that is where the nomination's central historical claim ran into trouble (see below). The village engineer told members the structure was found unsafe to stand on or operate in 2022 and again recently. The plan he described is to divert water around the island permanently and put a pedestrian bridge where the dam stands, possibly incorporating pieces of it — the old chains and gates — with signage explaining how it worked.
The commission's own doubts were about integrity, not age. The gates are long gone and were replaced every few years anyway; the deck was replaced around 2008; the hoist mechanism has changed at least once. Summing up, a member concluded “the only thing I can say for sure that's original is those piers” — and those, by the DPW's account, are badly deteriorated. Another put it more bluntly: “It's like a burned out building that we're looking to landmark.”
The hearing closed 5–0. Members agreed to arrange a site visit and to test the dam against the federal integrity criteria before deciding. It goes on the commission's December 15 agenda, at 7 p.m.
Under the village's landmark law, as the village attorney read it aloud Tuesday, once the commission closes a public hearing it has 32 days to make a determination on the proposed designation. That window can be extended only by mutual agreement of the commission and the property owner — and here the property owner is the village itself.
December 15 falls 28 days after Tuesday's hearing, inside the window. If the commission recommends designation, it must do so in writing, identifying the criteria met, and the Board of Trustees decides. The attorney also noted the unusual posture: a third party, neither owner nor commission, made this nomination.
The roll call is not reliable on this recording: the transcript has a reply for all seven members on the agenda — Anthony Bannon, Kathleen DeLaney, Raymond Herman, Catherine Waterman-Kulpa, Patrice Hannotte, Susan Fenster, Patricia Walker — but every tally announced was 5–0, and a member referred to the chair being back “next time.” The member presiding said she had only just learned she would chair. Who was absent is not established by the audio.[*]
Also present: the village attorney and Department of Public Works staff. Mayor Christine Hunt presented the final item.
Asked by the Village Board to search the archives, Stan Billings[*] of the Department of Public Works walked members through roughly a century of paperwork. It is the most complete public account of this structure this publication has heard, and several of its findings bear directly on the nomination.
The origin. A 1929 flood committee concluded that the best way to stop flooding in the village was to dig a channel about 70 feet wide along the old mill raceway, using the spoil to build what is now Island Park, and floated a flood-control structure. A special election approved buying land for $10,000; another approved bonding $90,000 for construction, carried 216 to 18. Billings put that at about $1.8 million in today's money.
Not the WPA. Near the end of the hearing he was direct about it: “There is no mention” of the Works Progress Administration in connection with the channel or the dam. The project was village-funded, bid out and built by a contractor. The WPA does appear in village minutes in 1933, he said, for a project further upstream and for tree pruning. A member noted the WPA itself dates to 1935. The nomination's description of the dam as a WPA job — repeated by its sponsor on Tuesday — is not supported by anything the village has found.
A long fight over water. Within about a year of completion, in 1931, the mill's operators claimed $20,000 in damages for lack of water, and a court judgment followed requiring the village to supply the mill a minimum flow — about 250,000 gallons a day, as Billings read it — except during floods. Upstream owners on Oak Grove complained of flooding in 1957; a resident in 1994 reported four feet of water in her basement. The superintendent of the day, in correspondence Billings displayed, asked the board in effect to choose between water for the mill and dry basements upstream. Requests to the Army Corps of Engineers in 1993, and to the state for a cost-sharing district, produced nothing on the record.
Gates, decks and a disappearing dam. The oak-plank gates rot and were rebuilt roughly every five years, at an average Billings put around $8,000–$10,000 a year; a 1977 invoice shows $2,910 for two lower sections. Conestoga-Rovers[*] proposed a new deck in 2008, and a steel deck on new I-beams was installed. In 2011 the village had the structure reclassified by the state from a low-hazard to a no-hazard dam. A separate structure, known as the Klein Dam[*], which diverted water toward the mill sluiceway, “mysteriously disappeared” sometime between 2009 and 2014; nobody has the full story.
Unsafe, and studied. The village's engineer advised in 2021–22 that the dam was not safe to use or to install gates on. A $63,000 state hazard-mitigation grant, through the Division of Homeland Security and Emergency Services, paid for a study by Gomez and Sullivan[*] of ways to keep water in both channels without the dam; it produced three options, including passive designs and flood benching. A 2022 estimate to restore just one of the concrete piers came to about $250,000, and the contractor was uneasy even at that, after sounding the piers brought concrete flaking off. Billings described operating the gates from experience: two men on a narrow, slippery gangway, the whole structure shuddering, and, when a gate jammed, sledgehammers “while you have thousands of gallons of water rushing directly beneath you.”
The gates have not been installed since spring 2022, and Billings showed photographs of the west channel's banks beginning to revegetate on their own.[*]
Two ideas carried the commission's discussion, and both cut against a structure that has been rebuilt piece by piece.
The 50-year line. Preservation practice generally does not treat anything under 50 years old as historic. A member applied it part by part: the gates are recent, the deck is from about 2008, the hoisting mechanism was modernised at some point — leaving the piers.
Integrity. The federal standards, set by the Secretary of the Interior, ask not just whether a place is old or associated with history but whether it still conveys that history through its location, setting, design, materials and workmanship. A structure can have a real story and still fail this test if too little of the original fabric survives. That is the homework members assigned themselves before December 15. A landmark designation, if it came, would require a certificate of appropriateness for any alteration and would make demolition far harder — which is exactly why the sponsor wants it and why the village's plan would be affected.
The commission's first hearing was on the nomination it initiated in August: the East Side Ellicott Creek Stone Retaining Wall, the 19th-century mill wall that runs behind four parcels from 5630 Main Street along Mill Street, a section of which has collapsed.
The owner of 5630 Main Street — the “Touch of Brass” building — sent a representative, Matt Dubois[*], speaking for Main and Middle Associates[*]. The owner is “not here tonight to oppose” the designation, he said, but there are unresolved questions about who owns the wall, since the creek itself is a village-owned parcel; he said the owner had a productive conversation with the village attorney that day and would work to clear up the title questions.
His substantive point was engineering. The wall is continuous across at least four properties, and piecemeal repair by individual owners, without a single plan, could damage neighbouring sections and the wall's historic integrity. He pointed to Project 18 of the village's adopted Local Waterfront Revitalization Program, which contemplates seeking state money, technical help and access easements for the repair, and urged a partnership among the village, the owners and state and federal agencies. A member noted that designation can open funding sources, and suggested he take the coordination point to the Village Board, since it is beyond this commission's reach.
A village resident spoke in support, citing the wall's link to the early mills and noting that original stonework, once lost, cannot be recreated. The hearing closed 5–0. No recommendation on the wall was voted Tuesday.
On the village's own Meeting House at 5658 Main Street, the pew-removal half of the pending certificate of appropriateness was withdrawn from Tuesday's agenda, leaving the interior paint scheme. Mayor Christine Hunt presented it with mock-ups: mostly white, with two lighter blues for larger areas and a darker colonial blue for fine detail; the original scrollwork at the front of the hall will not be painted. Members' questions were about what had previously been painted versus varnished — the brown panels at the back, it turns out, were already paint.
The recording ends in the middle of that discussion. Whether the commission voted on the paint certificate, and how, is not in this record.
Tallies are as announced from the chair. Five members voted on each recorded motion; the recording does not establish which two were absent. Mover and seconder are given only where the audio names them.
Moved by a member identified as “Ray” (Raymond Herman[*]); seconded by a member identified as “Patty.”
Two speakers: a representative of the owner of 5630 Main Street (not opposed; raised wall ownership and a corridor-wide repair plan under LWRP Project 18) and a village resident (in support). No recommendation vote taken; the 32-day determination window runs from the close of the hearing.
Citizen nomination presented by its sponsor; one speaker opposed; DPW archival presentation; the village engineer described the dam as unsafe and outlined a diversion and pedestrian-bridge plan. Seconded by a member identified as “Ray.” Members to hold a site visit and apply the federal integrity criteria. Determination due within 32 days unless extended by agreement with the village as owner.
Presented by Mayor Christine Hunt. The recording ends during members' questions; any vote, and adjournment, fall after it.
The recording is incomplete. It runs 81.5 minutes and stops during the final agenda item, the Meeting House paint certificate. Any vote on that item and the adjournment are not in this record. The opening line of the transcript gives the date as “October 17”; the agenda, the minutes approved (October 27) and the content confirm this is the November 17 meeting.
Roll call. The transcript shows a reply to all seven names, but every announced tally was 5–0 and members spoke of the chair returning “next time,” so attendance is not reported as fact. Member names are from the Village's official commission listing as recorded in this pipeline and the agenda's roll-call block; Whisper's “Waterman-Culpa,” “Hano” and “Delaney” are corrected to Waterman-Kulpa, Hannotte and DeLaney. The agenda lists Trustee Jeffrey Hahn as Village Board liaison.
Corrections against the agenda: “Eastside Ellicott Creek Stone Retaining Model” is the East Side Ellicott Creek Stone Retaining Wall; “Main Street Leading House” is the Meeting House, 5658 Main Street; “Fudge Control” is flood control; “WMPA/WTA” is the Works Progress Administration; “DISHES” is the state Division of Homeland Security and Emergency Services. “Touch and Brass” is rendered Touch of Brass, as the second speaker said it.
Names from audio only, marked [*]: the nominator, the 5630 Main Street representative and his firm (rendered unintelligibly and not printed), the owner entity, the DPW presenter, the engineering and consulting firms, and the Klein Dam. Two speakers, the opponent and the wall supporter, are not named. Figures in the DPW history are as read aloud from archival documents not available to this brief; the corrections file records the creek gates as removed in 2023, while the DPW said they were last left out in spring 2022 — the DPW's account is reported.
Street validation ran against the Amherst street list, which carries the Village's streets: Main Street exact; nothing else flagged. Bare street names (Mill Street, Oak Grove) were checked against the agenda and list by hand. Scanner-history lookups for 5630 and 5658 Main Street found only routine, unrelated calls.