Pass the Fire Inspections by December 31, or Lose the Tax Break on January 1

Lancaster's IDA chose an ultimatum over immediate termination: a Pavement Road storage park whose own resolution says it is out of compliance with the Town Code has until the end of the year to get its tenants inspected and remove a non-conforming gym — or the agency ends its PILOT on January 1.

“We've Made Some Missteps”

The Lancaster Industrial Development Agency held a resolution to end a PILOT agreement on its table for several months. On Tuesday it put that resolution aside and adopted a different one — not an acquittal, but a deadline.

The project is Pavement Road Storage LLC, at 515 Pavement Road. The agency induced it on August 10, 2021: land acquisition plus the construction and equipping of two pole barns totalling 26,455 square feet of office and warehouse space. Under the standard structure the agency took a leasehold interest in July 2022 and leased the facility straight back to the company.[2]

The resolution the board adopted states the problem on its own face, which is unusual candour for a document of this kind:[2]

“The Facility is not in compliance with the Town of Lancaster Town Code due to Shannon Connors Fitness being in violation with the Town Code and because several tenants have not responded to requests by the Town Building Department for Fire Safety and Property Maintenance Inspections.”

Two distinct failures, then. One is a zoning mismatch: the facility is approved as office and warehouse space, and the recitals note it operates that way “with the exception of Shannon Conners Fitness who operates as a retail operation.” The other is simpler and more serious — several tenants had not answered the Town Building Department's requests for fire safety and property maintenance inspections.[2]

A representative of the company addressed the board and did not dispute much. The facility is “hopefully… now in compliance with the exception of the Shannon Connors Fitness, but her lease expires the end of this year. We've told her it's not going to be renewed.” Letters had gone to the building department; tenants had been made to comply. And then the argument that IDAs are built to hear:[1]

“This is an investment of well over $2,600,000 into the town. We want to comply. I get we've made some missteps, but hopefully we've corrected all of those.”[1]

The board was offered a binary and took neither half of it cleanly. As the chair put it, the choice was “termination, or do you want to turn around and accept the new amended” consent resolution. A member moved the amended version with the reasoning stated out loud: “but again, if they don't meet the requirements then it's terminated anyway, right — as opposed to terminating immediately.” It carried 5–0.[1]

What that resolution actually does is consent to nine subleases, and then impose two conditions with a date and a consequence attached. By December 31, 2026 the company must remove the non-conforming gym from the facility and ensure its sublessees obtain all required Town of Lancaster operational permits and inspections. If it fails, “the Agency will terminate the PILOT Agreement effective January 1, 2027.”[2]

One board member asked the question that decides whether a deadline like this means anything: would compliance be self-reported, or verified? The answer was that “the building inspector will continue his efforts to schedule inspections” — and, pressed later on timing, that coordination with tenants and notice had been given, and the inspections would happen before the end of the year.[1]

That is the right question, because the original failure was tenants not responding to the building department. A deadline enforced by the same mechanism that had already been ignored would be worth very little.

The explainer: what a PILOT is, and why losing one bites

An industrial development agency cannot hand out cash. Its main tool is a PILOT — Payment In Lieu Of Taxes. The agency takes legal title or a leasehold in the property, which makes it exempt from property tax, and leases it back to the company. The company then pays the agency a negotiated schedule of payments, typically rising toward the full assessment over ten or fifteen years, and the agency passes that money to the town, county and school district.

The company also usually gets a sales tax exemption on construction materials and equipment, and a mortgage recording tax exemption.

Terminating a PILOT means the property returns to the full tax roll. For a 26,455-square-foot commercial facility mid-schedule, the jump is immediate and the company has no recourse — which is exactly why the threat is the agency's real enforcement power, and why holding the termination resolution on the table for months was itself a form of leverage.

In the Room

The agency has five members, all voting, verified from the resolution's own signature block: Chairman Kevin Lemaster, and members Grant Getzoni, Robert Leary, Frank Lutz and Patrick Sportelli. All five answered every roll call.

Every vote was taken by roll call — unusual for a body this small, and useful, because it means every position is on the record.

Agency staff and professionals took part throughout: counsel, who drafted both resolutions and the RFP; the executive director; and other appointed professionals. They are not named here — the recording gives most of them only a first name.

If they don't meet the requirements then it's terminated anyway — as opposed to terminating immediately.A member, moving the amended resolution[1]
A discrepancy in the operative text

The resolution's recitals identify the non-conforming tenant as Shannon Connors Fitness — spelled Conners in one paragraph and Connors in the next, within the same document. The company's representative also referred to Shannon Connors Fitness on the recording.[1][2]

But Section 2 — the enforceable paragraph, the one carrying the December 31 deadline — orders the company to remove “One-on-One Fitness” from the facility. That name appears nowhere else in the resolution and was not said aloud at the meeting.[2]

Most likely these are the same gym under a trading name, and the agency's intent is not in any doubt. But the recitals and the operative section name different businesses, and it is the operative section that would be enforced on January 1. This publication flags it rather than resolving it; the minutes, or a corrected resolution, should.

The Tax Break Nobody Would Claim

If the Pavement Road item showed an agency using its leverage, the next discussion showed the opposite problem: an agency unable to give away a benefit.[1]

A project induced last December, described on the recording as a dental venture, has an inducement that expires December 8 — the date of the agency's next meeting. Counsel laid out what has happened since, and it is a catalogue of non-response.[1]

The package went out last December: the project and agent agreement, the agency's sales tax bill, and the forms the company needed to sign and pay in order to start using its sales tax exemption. The reply, in counsel's account: “nothing.” Since then there have been five or six meetings, including one lasting “an hour, hour and 15 minutes last week” after which the company promised an answer within 24 hours. “I've called several times, and they have not returned my phone call.”[1]

Meanwhile the project is visibly being built. Agency representatives who visited saw entrances changed, “brand new steel that they bought and put up,” a section of concrete cut out and a footer poured, heavy beams raised and floor joists running across them.[1]

And every bit of that material has been bought with full sales tax paid. The company decided to proceed without bank financing but could still have used the exemption and taken the PILOT. Instead, as counsel put it, “they've been making sales tax purchases, paying full sales tax, for several months now. And I don't understand why.”[1]

A member asked the obvious question — can they go back and get reimbursed? The answer was one word: “Nope.”[1]

Why “nope” is the whole story

An IDA sales tax exemption is prospective and procedural. The agency appoints the company as its agent for purchases, and that agency appointment is what makes a purchase exempt. Buy the steel before the paperwork is executed and the purchase was never exempt — there is no refund mechanism, because nothing was wrongly collected.

This is why the agency's professionals said their standing instruction at every first meeting is “don't do anything until you get the paperwork.” The money lost here was not lost to a denial or a dispute. It was lost to unreturned phone calls.

Counsel's diagnosis was blunt: “I think there's a grave lack of communication within the company and with their own attorney as to what needed to happen,” with “so many emails back and forth asking where is this, this is what you need to do.” The chair's summary was gentler and more resigned — “all we can try to do is help” — and he noted the company could have asked for an extension if it needed more time. “Unfortunately, they're shooting themselves in the foot.”[1]

The board spent a few minutes on how to force an answer, and settled on asking the contractor, on the theory that “normally the person that's ordering the stuff will give you an answer” and that a building permit would show who is doing the work. One member was careful to mark the jurisdictional line — “it's not my job… that's the town's job” — before agreeing to check with the town.[1]

Counsel has agreed to bill the company at an hourly rate for the contracts drawn to date rather than the full project fee, if the project is closed out. One way or another the question resolves in December: a smaller project, or none.[1]

The Governance Committee, in Full

The agency has a governance committee and an executive committee. It also has five members in total, which the chair noted makes separate committee meetings somewhat theoretical: “we're only basically five people here… I can't see breaking them up into different meetings.”[1]

He asked whether both committees could simply sit as the full board, there and then. Counsel's answer was the correct one and the only condition that matters: “Sure… as long as it's done in an open meeting.” The chair's reason was sound too — “this way everybody's informed.”[1]

The governance committee's business then consisted of one question, asked three ways. Does anybody want to change anything in how we're doing business? Is everything we're doing working? Any ideas?[1]

The recording carries roughly ten seconds of nothing. Then: “There's nothing that you would say maybe we could do this a little differently or a little better? Nobody? No? Well, I guess that takes care of our governance committee.”[1]

Consolidating committees into an open full-board session is a defensible call — arguably a more transparent one than three separate meetings of overlapping members, and counsel confirmed the open-meeting requirement was satisfied. It is still worth recording that a public authority's annual look at its own best practices took under a minute and produced no comment, on the same morning the agency was dealing with a facility that had ignored its fire inspections and a company that had forfeited months of tax exemption through unanswered calls. Those are the circumstances in which a governance review has something to work with.

The executive committee, taken up immediately after, had actual business: recruitment. Agency board members are appointed by the Town Board, and the agency in turn appoints its own professionals. A councilmember had asked at the last town board meeting that applications for appointment be submitted by the end of this month.[1]

Everything the Agency Did — Click Any Row to Expand

Five members, all present, every vote by roll call. Where a motion's mover is identifiable on the recording it is described; the roll calls themselves are clear and complete.

— Pavement Road Storage — nine subleases consented, December 31 compliance deadline, PILOT terminates January 1 on failure Adopted 5–0

Consent to subleases between Pavement Road Storage LLC and nine tenants: Charles Donner d/b/a Curiosities Greeting Cards; Trevor and Fred McGrath; Thomas Nicotra; Performance Advantage Company; PanTech Micro Deburring; Yousef Salem; Eric Peterson; Code & Chrome Detailing; and Rams Remodeling & Construction.

Conditions, by December 31, 2026: remove the non-conforming fitness tenant from the facility, and ensure all sublessees obtain the required Town of Lancaster operational permits and inspections. Failure terminates the PILOT agreement effective January 1, 2027.

A competing resolution to end the PILOT outright, tabled for several months, was dropped rather than un-tabled and voted — the chair asked and was told to “just drop it.”

— 3525 Walden Avenue — eight tenants accepted Adopted 5–0

A parallel sublease-consent resolution for the agency's 3525 Walden Avenue project, covering eight tenants, against nine at Pavement Road. It drew no discussion at all — the contrast with the preceding item is the point: the same instrument, routine when a facility is in order.

The individual tenant names are in the agenda packet's resolution text and are not reproduced here, since no issue was raised about any of them.

— 2027 budget — adopted, with the Town Supervisor passing over union negotiations Adopted — one member passed

Described from the dais as a finalisation rather than a fresh approval — “it was approved, we're just finalizing it.” The budget does not appear on the posted agenda.

Member Robert Leary passed rather than voting, explaining: “we still haven't finished our negotiations with the white collar at this point, so I'm going to pass on this, because we're changing the amounts for people.” Mr. Leary is also the Town Supervisor, so he sits on both sides of that negotiation; passing on a budget that sets compensation while bargaining is unresolved is a conservative and appropriate handling of it. The chair pressed once — “yeah, I know, but again” — and Mr. Leary held his position.

This brief does not report a tally for this item. The roll call is audible but the responses after the pass are clipped, and a budget adoption deserves a tally this publication can stand behind. The minutes will carry it.

— RFP for Palmer Place and Commerce Parkway — tabled pending talks with the Village Tabled

Counsel has drafted the RFP for Palmer Place only, wanting the board's input before generating the parallel document for Commerce Parkway. The project is a joint undertaking with the Village of Lancaster, and the agency has not yet spoken to the village about how much input it wants or what parameters belong in the RFP. The board preferred an initial approach to the mayor directly over attending a village board meeting.

Tabled “until we get more information.” The board's substantive steer: the agency keeps control of the site, with a prospective tenant able to put improvements in and out at its own cost while the agency picks up the bulk.

Asked whether an application exists for Palmer Place, the board described possible interest from a hotel supply company — and immediately discounted it: “that was a rumor, so that's all we can go by.” No applicant is reported here, for that reason.

— Vouchers, October 2026, and the October 13 minutes Accepted 5–0

The October vouchers were moved, seconded and carried 5–0 by roll call in the meeting's opening seconds. No dollar total was stated aloud. The voucher and budget pages of the agency's agenda packet are scanned images with no extractable text, so no figure is reported here.

The agenda also lists presentation and approval of the October 13, 2026 minutes and a CFO report; neither is identifiable as a separate discussion on the recording, which opens mid-motion.

— Project pipeline — a $1m-plus toolmaker, a stalled dental project, and two Canadian companies watching tariffs Discussed; no action

Pattern and Tool, currently at 21 Pavement Road: a prospective new facility in the Village of Lancaster, which the board put at over $1 million, adding five to six jobs. The business runs woodworking, turning and CNC at the front of its present building and metalworking machinery including five-axis CNC at the back, and has run out of room. It does a good deal of work for Kittinger. The principal was meeting bankers; the agency offered help with that.

The threshold, stated plainly: a project needs to reach roughly “a million dollars” before agency assistance is worth the applicant's while — “then you start saving money after that. Anything below that, you're kind of pushing numbers around.” A useful figure for any Lancaster business wondering whether to approach the agency.

The stalled project — induced last December, inducement expiring December 8 — is covered above. Buffalo Wholesale: no response yet. Two Canadian companies: “very concerned about the tariffs and stuff like that.”

Site locations given for the toolmaker rest on approximate oral description and are not printed as an address.

— Governance and executive committees — both held as the full board, in open session Held; no action

With five members in total, the chair proposed both committees sit as the full board rather than meeting separately; counsel confirmed this is acceptable provided it is done in an open meeting. Governance: the chair invited suggestions on the agency's practices three times and received none. Executive: member recruitment, with the Town Board asking for appointment applications by the end of November.

No public comment was offered when the chair opened the floor. The meeting adjourned 5–0, with thanks to veterans ahead of Veterans Day.

By the Numbers
Dec 31Deadline for inspections and removing the non-conforming gym
Jan 1Date the PILOT terminates if the deadline is missed
$2.6m+Investment the company says it has made in the town
26,455Square feet in the two pole barns the agency induced in 2021
9 / 8Subleases consented at Pavement Road and at 3525 Walden Avenue
~$1mProject size the agency says makes its assistance worthwhile
5–6Jobs a prospective toolmaking facility would add
0Suggestions offered when the governance committee asked
Editor's Note

The agenda packet did most of the work here, and it should be said why that matters. This agency publishes a full packet carrying the complete text of its resolutions — recitals, operative sections, signature blocks — rather than a one-line notice. Nearly every hard fact in this brief came from it: the 2021 inducement date, the 26,455 square feet, the nine named sublessees, the December 31 and January 1 dates, the compliance findings, and the five members' names and titles. A 17.8-minute recording of a meeting whose participants already knew all of that would have yielded a far thinner and less accurate brief on its own.

The roster is verified from an official document rather than audio. The resolution's signature block names Chairman Kevin Lemaster and members Grant Getzoni, Robert Leary, Frank Lutz and Patrick Sportelli. The transcriber mangles several of these — Getzoni appears as “Gattoni” and “Yatoni,” Sportelli as “Spartelli” and “Spritelli,” Lemaster as “Jalen Master” — and all are corrected silently against the signature block. This also corrects a spelling this publication previously had to flag as unverified on a September brief.

Agency staff and professionals are not named. Counsel, the executive director and the other appointed professionals are referred to on the recording almost entirely by first name, with no surname and no official document here to confirm them. Their contributions are reported in full and attributed by role. Where a first name is the only identifier available, this publication does not print it.

Two numbers a reader might expect are missing, and the reason is the same one. No voucher total and no 2027 budget figure appear in this brief: neither was stated aloud, and the voucher and budget pages of the agenda packet are scanned images with no text layer, so they cannot be read without optical character recognition that this brief did not attempt for figures of this kind. This is a known characteristic of this agency's packets and is recorded in the pipeline's notes.

Where the agenda and the meeting diverge. The posted agenda lists Old Business as NONE and New Business as NONE, yet the board worked through the stalled dental project, the Pattern and Tool prospect, Buffalo Wholesale, two Canadian enquiries and both committee meetings under those headings. The 2027 budget adoption is not on the agenda either. None of this is a fetch failure — the agenda was retrieved intact and is reproduced faithfully; the board simply transacted business the notice did not forecast. It is the second time this publication has recorded that pattern in Lancaster.

The stalled project's name is withheld. The company was named on the recording only in a form the transcriber plainly mangled, and it is not identified in the posted agenda. An unflattering account of a company's failure to answer its telephone is not something to attach to a name this publication cannot verify. It is described by sector, as the board described it. The agency's next meeting, December 8, should resolve the matter on the record.

Capture. 17.8 minutes, 349 segments, language confidence p=0.999, effective coverage 89.0% with no segment spanning dead air. This board is transcribed with the “large-v3” model and voice-activity detection disabled, because Lancaster's room microphone and crosstalk defeat the default settings. The recording opens mid-motion on the vouchers, so the call to order and roll call are not captured; the five roll-call responses on that first motion establish that all five members were present from the start.

What official minutes would add: the voucher total, the 2027 budget figure and its tally, the exact wording of the budget member's pass, and whether the One-on-One Fitness reference in Section 2 is corrected.

Overheard
  • “I get we've made some missteps, but hopefully we've corrected all of those.” — for the company[1]
  • “If they don't meet those conditions by the end of the year, we will terminate the pilot in January.” — counsel, summarising the resolution[1]
  • “Can they go back and get reimbursed?” / “Nope.”[1]
  • “I call, I email, I get no response from them.”[1]
  • “Don't do anything until you get the paperwork.” — the standing instruction to every applicant[1]
  • “All we can try to do is help… unfortunately, they're shooting themselves in the foot.”[1]
  • “Nobody? No? Well, I guess that takes care of our governance committee.”[1]
  • “That was a rumor, so that's all we can go by.” — on interest in Palmer Place[1]
Sources
[1] lancaster_LIDA_20261110_transcript.txt — audio of the Town of Lancaster Industrial Development Agency regular meeting, Tuesday, November 10, 2026, 9:00 a.m. (17.8 minutes). faster-whisper “large-v3” model with voice-activity detection disabled, language confidence p=0.999, 349 segments, effective coverage 89.0%. Source for every quotation in this brief and for all five roll calls. The recording opens mid-motion.
[2] lancaster_LIDA_20261110_agenda.pdf — the agency's own 15-page agenda packet, retrieved from the Lancaster IDA public documents centre. Carries the meeting order and the full text of the Pavement Road Storage resolution, including the 2021 inducement date, the two-pole-barn 26,455-square-foot project description, the July 2022 Lease to Agency and Leaseback Agreement, the nine named sublessees, the Town Code compliance findings, the December 31, 2026 conditions and the January 1, 2027 termination provision, and the five members' names and titles in the signature block. Also the source for the next meeting date, December 8, 2026 at 9:00 a.m. The voucher and budget pages are scanned images with no text layer.
[3] Roster verified from the resolution signature block in [2], an official agency document, superseding the audio-only spellings previously carried in this pipeline's Lancaster corrections file.
[4] The explanations of how a PILOT is structured, why terminating one returns a property to the full tax roll, and why an IDA sales tax exemption cannot be claimed retroactively are this publication's own, offered as general New York context. They were not stated at the meeting and are not legal or tax advice.
[5] Official minutes for this meeting are the authority for the voucher total, the 2027 budget figure and tally, attendance as formally recorded, and the identity of the stalled project. They were not available to this brief; the agency's minutes typically post about a week behind.
[*] Indicates a proper noun corrected from a known transcription homophone or resting on audio alone. Verify against the agency's official record before quoting in any formal communication.
WNY Listening Post · The Public Record · Lancaster Edition · Compiled 2026-11-13
Compiled from public meeting transcripts; transcriptions are AI-generated and may contain errors. Names, dates, dollar amounts, and details should be verified before action.